negative time entries
We do a monthly cutoff for financial reporting. When it is discovered that time has been entered to a project incorrectly after the month...
  • 1 me too
  • 3 replies
  • Problem
  • Solved
Photo of JJ
Progress report at task level not available
I want to create a report that shows actual hours versus estimated hours for all of the tasks on a project. The actual hours I want to sh...
  • 3 me toos
  • 9 replies
  • Problem
  • Acknowledged
Photo of Swalve, Randy
Unable to add a timesheet for a team member that is on vacation with the latest release of Replicon. How do I do this for them?
Prior to this release of Replicon, I was a substitute user for all my team to go in and check on time, enter a time sheet, etc.  As of no...
  • 1 me too
  • 1 reply
  • Problem
  • Solved
Photo of White, Karen
Disabled users on Payroll Workbench
Approved time off bookings are coming through to the payroll workbench for disabled users.  This does not make any sense, surely the poin...
  • 1 me too
  • 2 replies
  • Problem
Photo of BOTTI, HUDSON
Expense tab
There is no expenses tab in my Replicon. What need I do to configure it?
  • 1 me too
  • 2 replies
  • Problem
  • Solved
Photo of White, Linda
I have been trying to enter time off but it doesn't locate my name on drop down menu. Help!
Trying to enter PTO but no name option.
  • 1 me too
  • 1 reply
  • Problem
  • Solved
Photo of Paulsen, Andrea
Expense Editing Issues
I have an issue with editing large expense reports. Our corporate visas have several line items and multiple projects but we need to keep...
  • 1 me too
  • 2 replies
  • Problem
  • Acknowledged
Photo of Kessler, Carolyn
Time off setting for V1 version
We are using the V1 version for time off. We would like to be able to add a "Yearly Carry Over with Expiry" to a time off type. Apparen...
  • 1 me too
  • 4 replies
  • Problem
  • Acknowledged
Photo of Moreno, Ivan
Ordinary day overtime issue
Hello team I have the following issues with my timesheet: I have to work 45 hours ordinary time, but today I found my manager rejected ...
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of Bann, David
Only Take Billable Time into Account for Project/Task Estimates Validation
We have the "Project/Task Estimates" validation enabled on our timesheets. The problem we find is that all hours, including non-billabl...
  • 2 me toos
  • 4 replies
  • Problem
  • Acknowledged
Photo of Ballard, Elaine
Error message when a user is asked to approve their own timesheet after it's been edited by another PM
Support have told me that it's "system behaviour" that a user is being asked to but can't approve their own timesheet if it was edited by...
  • 1 me too
  • 4 replies
  • Problem
  • Acknowledged
Photo of Sonja Cicchetti
Banking overtime hours in gen 2 vs. gen 3
In gen 2 we were able to specify how many hours we wanted to bank and how many hours we wanted to be paid out however in gen 3 you only h...
  • 2 me toos
  • 1 reply
  • Problem
  • Solved
Photo of Wheeler, Karen
custom column add different leave types won't add up yet have selected "sum" in setup
Custom column will not add up
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of Isnor, Peggy
Resources - No view permission for just the resources
We use the resources module to schedule a team of 20 people. These people need to see the schedule, but they should not have access to al...
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of Barker, Dan
Report on Unallocated Resources
We can't report on unallocated resources which is a huge staffing problem for us. We want to be able to pull a report of resources that a...
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of August, Dan
web services documentation
Developers really need some documentation for your web services, particularly on: What is the intended purpose for each web service oper...
  • 5 me toos
  • 1 reply
  • Problem
  • Acknowledged
Photo of ANDERSON, LISA
Confusing, extra step and incorrect labels
Our users find it really confusing that once they click onto a project and try to choose a task, they cannot click on task rather it is l...
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of Peter Flinn
Administration - create a standard Task list
We utilize a standard Task list across all projects (not all projects have the same set of Tasks, but they are drawn from the same list),...
  • 1 me too
  • 2 replies
  • Problem
  • Acknowledged
Photo of Garcia, Ainara
Customize the date range in the time off balance history
Hello, we wonder about the possibility of customizing the date range in time off balances  to show the whole current year, I mean "01 Jan...
  • 1 me too
  • 1 reply
  • Problem
  • Acknowledged
Photo of JJ
Billing Template report should have Approval Status filter
The Billing Template does not offer the filter of "Approval Status".  This means the report can be run with the result of time or expense...
  • 1 me too
  • 2 replies
  • Problem
  • Acknowledged