Resource Forecasting

  • 1
  • Question
  • Updated 6 months ago
  • Answered
Has anybody figured out a way to forecast resource deficits or overages utilizing the resource allocation component in replicon? 
We would like to utilize the project summary graph to look forward and show need versus actual allocated resources to the project OR program. 
Is there a way to do this?  
Appreciate thoughts & ideas.

Thanks!

Julie
Photo of Samsel, Julie

Samsel, Julie

  • 7 Posts
  • 0 Reply Likes

Posted 8 months ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1583 Posts
  • 108 Reply Likes
Hi Julie,

We would like to understand the way you would like the resource need to be calculated.

Thanks,
Aashnee
Photo of Samsel, Julie

Samsel, Julie

  • 7 Posts
  • 0 Reply Likes
We would like to be able to create a graph on the summary page of the project or program, that looks forward to the next week, month, quarter, (or whatever forward timeframe you want to see) and includes: actual allocated resources. placeholders, and looking at the past includes actual hours compared to the allocated hours projected. Does that make sense?
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1583 Posts
  • 108 Reply Likes
HI Julie,

Unfortunately, this is not something that we can currently accomplish in the system. The only way out is to create a report and export them to fulfil the requirements.