A team member was added to a project, but the project isn't displaying on her timesheet.  Is there a limit to the number of members on a project? Why would it not show up and more importantly how can we make it display?
Photo of McBride, Annette

McBride, Annette

  • 10 Posts
  • 2 Reply Likes

Posted 4 months ago

  • 1
Photo of Drema Herron

Drema Herron

  • 61 Posts
  • 15 Reply Likes
Is the project "in progress" status? Is the team member assigned to the task? Is the "allow time entry" box checked? Is the task open? Are there date limitations on the project or task? Did the employee refresh their time sheet? 
Photo of McBride, Annette

McBride, Annette

  • 10 Posts
  • 2 Reply Likes
Thank you! The task was the issue.  This is the first project we have used with tasks.
Photo of Drema Herron

Drema Herron

  • 61 Posts
  • 15 Reply Likes
you'll have a lot more analytical power using tasks and sub-tasks