Project Burndown Report - Baseline Estimated Hours

  • 1
  • Question
  • Updated 3 years ago
  • Answered
Where are the Baseline Estimated Hours being defined that are displayed in the Project Burndown Report?
Photo of Paul

Paul

  • 1 Post
  • 0 Reply Likes

Posted 3 years ago

  • 1
Photo of Lingaraj Dharwad

Lingaraj Dharwad, Product Champion

  • 1100 Posts
  • 46 Reply Likes
Hi Paul,

Thank you for using Replicon community,

The Baseline Estimated Hours column shows the Estimated Hours set at the Project Level for the first period (week, month, quarter) and for the next period the Baseline Estimated Hours would be the difference between the Estimated Hours and the Actual hours for that period.
 E.g. : Suppose the Estimated Hours for a Project is 2385 and the Actual Hours for the month of February is 5.

Then the Baseline estimated Hours for February would be 2385 and that for February would be (2385 -5)=2380 and so on.

 Screenshot :




Hope that helps.

Thanks,
Lingaraj