We are updating all our timesheet templates and we noticed that this option "Keep timesheets in sync with resource allocation" in Timesheet templates.

What exactly does this option do?  Does this only allow a person to log time against a taks if they are allocated against that task?
Photo of McMurray, Edward

McMurray, Edward

  • 2 Posts
  • 0 Reply Likes

Posted 3 months ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1372 Posts
  • 97 Reply Likes
Hi Edward,

This options adds the user’s project allocated hours (the hours allocated in the resource calendar) to display automatically in their timesheet. Timesheet hours update when allocations are updated.