Hi All,

How to set up weekly notification for a Manager when their team members have not submitted their time-sheets?

Thanks.
Subhadeep Kundu.
Photo of Kundu, Subhadeep

Kundu, Subhadeep

  • 2 Posts
  • 0 Reply Likes

Posted 2 years ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1439 Posts
  • 102 Reply Likes
HI Subhadeep,

Thank you for using the Replicon Community!

This can be achieved by having the supervisors create a report and schedule it weekly. They can follow the below steps:

- Go to Reports
- Add a new report
- Choose Category as Timesheet and report type as timesheet day template
- Add User Name, Timesheet Period and Approval Status



- Click create and click on the Edit button next to Filters
- Choose the filters "Approval Status" and "Timesheet Period". Click done editing



- Filter the approval status to show only open status




- Filter the timesheet period to show "Last Timesheet Period"


- Run the report and save the report
- Click on Set Schedule 



- Set the schedule as follows (you can choose the name, schedule date)



- Click Save and the supervisor will receive the list of timesheets which are open for the previous timesheet period

Thanks,.
Aashnee
Photo of Kundu, Subhadeep

Kundu, Subhadeep

  • 2 Posts
  • 0 Reply Likes

Thanks a lot for the steps.


It provides a report of all sheets but can we have a weekly email notifications for managers when any of their team members' timesheet is more than 1 week overdue?


Thanks again.
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1439 Posts
  • 102 Reply Likes
Hi Subhadeep,

Yes. You can add a timesheet period filter and filter the report for last week. So it will show all the last week's timesheet that are in open status. Once you add the filter, save the report and then add a schedule.

Thanks,
Aashnee
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1439 Posts
  • 102 Reply Likes
Hi Subhadeep,

Yes. You can add a timesheet period filter and filter the report for last week. So it will show all the last week's timesheet that are in open status. Once you add the filter, save the report and then add a schedule.

Thanks,
Aashnee
Photo of Nuno Ferreira

Nuno Ferreira, Champion

  • 193 Posts
  • 52 Reply Likes
Hi Aashnee!

Is there a way to send this report to all supervisors (role) and send only their resource's timesheets?

Thanks,
Nuno
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1439 Posts
  • 102 Reply Likes
H Nuno,

Currently if as an Admin you schedule the report, it is not possible to send the report to the supervisors for their respective resources. However, if a supervisor himself schedules a report, the report is scheduled and sent only for his team members.

Aashnee
Photo of Nuno Ferreira

Nuno Ferreira, Champion

  • 193 Posts
  • 52 Reply Likes
Right!

Thanks Aashnee!

Nuno