How to enter time with each project

(Originally posted by facevedo)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi,

Thank you for using Replicon Community.

A user assigned to tasks of a project should be able to enter time against the Project/Task in the Timesheet.
The User/Resource logs into Replicon and should follow the steps below.

  • Click on My Replicon tab in the top menu.
  • Select the Timesheet tab.
  • Click on the date range and select the Timesheet period.
  • The Timesheet generates automatically.
  • Now, click on the + sign beside Program.Project.Task.
  • A blank row is added below.
  • In the new row, under the Program.Project.Task column, click on <No Program>.<No Project>.
  • In the drop down, select the Program > Project > Task.
  • Now enter time in the Day/Date column for the Program . Project . Task.
  • Similairly multiple rows can be added for different Programs . Projects . Tasks, and time entered against them.