How to defined Task level Estimated Hours?

(Originally posted by iwarn2014)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes

Posted 4 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes
Hi,

Thank you for using Replicon Community.

Please find the steps below to update task level estimated hours:-

1. Log into Replicon as Project Manager with Edit projects/tasks permissions.
2. Go to Projects > Click on the required project.
3. Click on Edit project button under project structure.
4. You can update the Project level estimated hours from this page.
5. Click on save.

6. To update task level estimated hours, click on the required task name.
7. Update the estimated hours as needed and click on save.

The below video shows these steps:-



Thanks,
Lingaraj




(Originally posted by Lingaraj Dharwad)
Photo of Lingaraj Dharwad

Lingaraj Dharwad, Product Champion

  • 1100 Posts
  • 46 Reply Likes
Hi All,

Video is available below: 





Thanks,