Task Estimated Hours

  • 1
  • Problem
  • Updated 1 year ago
  • In Progress
I am using report type: "Task Time, Expense, Cost & Billing data" template to pull actual to estimated hours per task. I edit the "Date Range" to pull hours for a specific period only, but when I do this the estimated hour are altered as well. It appears that the estimated hours are only included on the report if time has been entered against the associated task during the specified "date range". I would like for the estimated hours to remained "fixed" while adjusting the date range for the actual hours. Is there a way to do this? 
Photo of House, Nicole J

House, Nicole J

  • 16 Posts
  • 2 Reply Likes

Posted 1 year ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1485 Posts
  • 105 Reply Likes
Hi Nicole,

Please include a filter called "Data to Display" and provide the filter value as "Show all data". 

Let us know if that helps you achieve the required report

Thanks,
Aashnee
Photo of House, Nicole J

House, Nicole J

  • 16 Posts
  • 2 Reply Likes
Unfortunately this does not help. If I set the Date Range to "Entire Project", that seems to be the only way to pull all the estimated hours by task. However, I only want to analyze a three month period not the whole project.
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1481 Posts
  • 104 Reply Likes
Hi Nicole,

I may need further clarification on the same. Can we have a short call scheduled?
Photo of House, Nicole J

House, Nicole J

  • 16 Posts
  • 2 Reply Likes
That would be great. Are you available tomorrow?