How do I set user rates independent of the users set rate or the projects set rate. Often users have a different rate for project A and Project B, and projects will have many users assigned to them who all have different rates. Thanks

(Originally posted by pstudart)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi,

Thank you for using Replicon Community.

Its possible to setup a custom user rate under the Billing Rates tab in the project section. Steps are as follows:-

1. Click on the required project under the project management tab.
2. Go to Billing Rates tab.
3. Click on + Add Billing Rate > Select User Rate.
4. Go to Team tab > Click on the users name under the Billing Rates column > Deselect Project Rate & select User Rate.
5. Go back to Billing Rates tab > under the Hourly Rate column > click on the amount and set the required amount and effective date.

Thanks,
Lingaraj