While viewing reports, I keep seeing my sub-tasks being categorized together rather than being separate and attaching itself to the parent task. How do I use the proper set up to see the sub-tasks together?

(Originally posted by HCrawley)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes

Posted 4 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes
Hi,

Thank you for using Replicon Community.

This is caused if report is grouped by Task Name.

Steps to remove the Task Name grouping are shown below:-

1. Click on 'Settings' button. 



2. Click on 'Grouping' drop down and remove the Task Name grouping. 



 

 

 

 

 

 

 

 

Thanks,