Hello,
In Project Management/Resources, when we switch to Weekly planning, we are unable to enter 'Total hours' per week, instead we have to enter total hours per day, or %.
When we plan, we do that on a week by week basis, so we want to be able to enter 2 hours per week. Right now, this is not available.
If you switch to monthly planning, it's available.

Also how can you eliminate the task selection after allocating the hours?
Photo of Ahmed AlTaie

Ahmed AlTaie

  • 14 Posts
  • 4 Reply Likes

Posted 3 years ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1617 Posts
  • 110 Reply Likes
Hi Ahmed,

Thank you for using Replicon Community!

While I will mark the first option as an idea and forward it to our product management team, please find the answer to your second query below:

Go to Administration
Click on Permission Sets
Open the Resource Manager permission set assigned to the user
Uncheck the options for Resource Task Allocations

Thanks,
Aashnee Kamboj
Photo of Ahmed AlTaie

Ahmed AlTaie

  • 14 Posts
  • 4 Reply Likes
Thanks Aashnee. The solution provided worked.

Also for the resources, we would like to see actual hours below the forecasts in the same view, and the total hours assigned to the project (forecast) as well as total billed/used at the end of the right column.
Is this something that will be done? as I noticed that this feature have been asked by other people earlier sometime back.
Photo of Ahmed AlTaie

Ahmed AlTaie

  • 14 Posts
  • 4 Reply Likes
Hi Aashnee,
What's the usual turnaround time for implementing ideas? Also, did you have the chance to review the other feature that we would like to see?
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1617 Posts
  • 110 Reply Likes
Hi Ahmed,

Ideas are first sorted and then looked upon based on the need and implementation turn around. There is no promised time line for this. Also we do not promise any idea to be implemented for sure. It depends on the necessity of the idea globally around all customers.