Reports

  • 1
  • Question
  • Updated 3 years ago
Hello, I would like a column added to my Detailed Task Report. The column needs to calculate Percentage Completion. Would you please assist me with this?

(Originally posted by Katherine.Harrison)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi

Thank you for using Replicon Community.

You can setup a custom column with the below formula. 

  • Go to Report Settings. 
  • Click on Custom.
  • Click on + Add a new custom column. 
  • Enter the formula (ActualHours/ProjectEstimatedHours)*100
Please find the screenshot with steps illustrated:- 



Provided you are calculating percentage completion for projects, below screenshot is how you will get the data. 





Thanks,





 

(Originally posted by Lingaraj Dharwad)