Questions on Resource template Gen3

  • 1
  • Question
  • Updated 3 years ago
Created a report based on Resource template, gives information on Allocation hours, Estimated hours (Selected date) without project name on it. Please advise.

(Originally posted by jodie.owen)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi Jodie,

Thank you for using Replicon Community.

Currently, Project Name column is not available in the Resource Template. A suggestion has already been raised for the same. Alternatively this can be setup using the 'Project Team Assignment template' which allows you to get the data for Project Name, Allocated Hours & Estimated Hours as shown in the screenshot below.  



Steps to add a new report are as follows:- 

- Log into Replicon as an Administrator/Project Manager.
- Go to Reports tab.
- Create a new report using +New Report option, based on Category:Project Report Type:Project Team Assignment template.

(Originally posted by Lingaraj Dharwad)