Hi Kellie,

Thank you for using Replicon Community.

You can create a new report based on Task Time, Expense, Cost & Billing data Template, enable the Actual Billing (Selected Dates) & other columns as required. Group Rows by User Name. 

1. Log into Replicon as a user with Billing Manager/Project Manager permissions. 

2. Go to Reports tab. 

3. Click on + New Report. 

4. Select Category as Project & Report type as Task Time, Expense, Cost & Billing data Template





Thanks,

Lingaraj



 