Earlier the Project leader was receiving and viewing the timesheets. For one week, the Project leader didn't see the timesheet. This timesheet only mentions Time off. The approval path set up is Supervisor and than project leader. Supervisor for this user is someone else. The timesheet had already been approved by the supervisor, but the project leader cannot see it.

(Originally posted by v.deswaef)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi,

Thank you for using Replicon Community.

In Replicon a Project leader can only approve Time entries in a Timesheet, but not Timeoff.
Hence, in your case, since there were only Timeoff entries in the timesheet, the Project leader did not receive the timesheet for approval.