issues getting the Activity selected to the Time Distribution portion of their time sheets .

  • 1
  • Problem
  • Updated 5 months ago
  • Solved
  • (Edited)
i'm having issues getting the Activity selected to the Time Distribution portion of their time sheets . the only way i can get the activity to show up is to manually select the activity and add the hours . is there any other way to automate this




Photo of FULTON, RODERICK

FULTON, RODERICK

  • 3 Posts
  • 0 Reply Likes

Posted 5 months ago

  • 1
Photo of Aashnee Kamboj

Aashnee Kamboj, Community Moderator

  • 1516 Posts
  • 106 Reply Likes
HI Roderick,

There should be a button called Overwrite with available on the top of your timesheet. Click on the button and choose the "Allocate timesheet hours" option. This should take care of the activity coming over to the time distribution section