How to calculate Project Cost Variance ?

(Originally posted by nsquittieri)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes

Posted 4 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 6 Reply Likes
Hi,

Thank you for using Replicon Community.

Using a report based on Project Time Analysis template this can be calculated by creating a custom column with the below formula:- 

ProjectBaseEstimatedCost-BaseBillableAmount





Thanks,

Lingaraj



 