Gen3: how to create a report to check the poject estimated hrs vs the actual hrs?

(Originally posted by demmett)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi Daniel,

Thank you for choosing Replicon Community!

If you have access to run reports, you can use the report template " Project Team Time, Expense Cost and Billing Template" to get the data.

Follow the steps below, to run the report.

>Click on the Report tab
>Click on "New Report"
>Under category Select "Project" and under Report type select "Project Team Time, Expense Cost & Billing template"
>Under Columns add only Client Name, Project Name, Project Estimate Hrs, User Name and Actual hours(Selected Dates) with Summary options set to "Sum".
>Under Grouping set "First by" to "User Name"
>Clcik on Done
>Click Edit next to the filter to enable/disable the required filter options.
>Select the filter options and run the report
>Click on the save to and save the report
>Click and Share button and select the names to share report with other users.