Need help to identify where is estimated Hours picked up from? Estimated Hours are not mentioned on the Project, but shown while running Reports.

(Originally posted by Katherine.Harrison)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi Katherine,

Thank you for using Replicon Community.

The Estimated hours are shown based on below aspects:   - If you have Professional Services Management (PSM) module/Project and Program Management (PPM) module, the estimated hours will be shown based on the resource allocation.   - If you have TimeBill module/TimeCost module, the estimated hours will be shown based on the task allocation. Thanks,