Different rates for a user in project

  • 1
  • Question
  • Updated 3 years ago
  • Answered
Hi!

I need to have different rates for a given user in a project, depending on where the work is done.

If he is working on a task in our company the applied rate will be one and if he is working on the same task but on the customer premises, the same resource will have another rate. In a given week he can work in house and out many times.

Does Replicon supports this kind of behaviour?

Thanks!
Nuno
Photo of Nuno Ferreira

Nuno Ferreira, Champion

  • 193 Posts
  • 52 Reply Likes

Posted 3 years ago

  • 1
Photo of Lingaraj Dharwad

Lingaraj Dharwad, Product Champion

  • 1100 Posts
  • 46 Reply Likes
Hi Nuno,

Thank you for your post. Currently, you can't have 2 users rates with different rates active at the same time. We instead recommend that you create a separate billing rate specific to this user and apply the same to this user as shown in the screenshot below:





This will allow the user to select the required rate. 

Regards,
Lingaraj
Photo of Nuno Ferreira

Nuno Ferreira, Champion

  • 193 Posts
  • 52 Reply Likes
Hi Lingaraj!

Thanks for the suggestion. I'll give it a try.