We have created this report in Gen3 as I use this often however it is missing a column. Currently this report has the following columns: Project Name User Name Entry Date Actual Hours (selected dates) In Gen2, the report added up all hours worked (summary)for all hours worked but I cannot find this feature/column in the report settings. Can anyone help?

(Originally posted by Katherine.Harrison)
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes

Posted 3 years ago

  • 1
Photo of Archived Post

Archived Post, Official Rep

  • 2132 Posts
  • 5 Reply Likes
Hi,

Thank you for using Replicon Community.

To set up summary of a column in a report:

  • Navigate to the Settings Tab of the report.
  • The Columns Section displays Selected Columns and Summary Options.
  • Beside the Actual Hours(Selected Dates) column click on the drop down menu under Summary Options and select Sum.
  • Click on the Done button to save the settings.


Thanks