Actual Hours column should deduct the all vacations of resource and should provide only the real available hours for that resource, which will help the resource managers to know the actual capacity available during that period and plan for work only for real available hours
- 7 Posts
- 0 Reply Likes
Posted 4 years ago
Lingaraj Dharwad, Product Champion
- 1100 Posts
- 46 Reply Likes
Hi Premnath,
Thank you for using Replicon community.
Actual Hours are currently calculated only for the time entered against projects. Are you referring to Actual Available Hours instead?
Regards,
Lingaraj
Thank you for using Replicon community.
Actual Hours are currently calculated only for the time entered against projects. Are you referring to Actual Available Hours instead?
Regards,
Lingaraj
- 7 Posts
- 0 Reply Likes
Hi Lingaraj,
yes i was referring to the Actual Available hours, it should be simple math if i got it correctly, number of hours for that month based on location - Time Off hours
Thanks & Regards,
Prem
yes i was referring to the Actual Available hours, it should be simple math if i got it correctly, number of hours for that month based on location - Time Off hours
Thanks & Regards,
Prem
Lingaraj Dharwad, Product Champion
- 1100 Posts
- 46 Reply Likes
Hi Premnath,
In the Resource template report type which contains the column Timeoff taken Hours (Selected Dates). This can be used to create a custom column with formula ActualAvailableHours-ActualTimeOffTakenHours. This should give you what you're looking for.
Refer to the image below:

Let me know if that helps.
Regards,
Lingaraj
In the Resource template report type which contains the column Timeoff taken Hours (Selected Dates). This can be used to create a custom column with formula ActualAvailableHours-ActualTimeOffTakenHours. This should give you what you're looking for.
Refer to the image below:

Let me know if that helps.
Regards,
Lingaraj
- 7 Posts
- 0 Reply Likes
Hi Lingaraj,
Thats what i tried the issue is Stat holidays is taken count in both the fields which is causing the mismatch in numbers, i mean if we have the stat holiday for a month, Actual Available hours will deduct that and Time Off field also counts that.
Thanks & Regards,
Prem
Lingaraj Dharwad, Product Champion
- 1100 Posts
- 46 Reply Likes
I will get this checked with the PM team and reply shortly.
- 53 Posts
- 10 Reply Likes
Hi Premnath,
Thank you for the feedback! We will consider this for our future release.
Regards,
Sangeet
Thank you for the feedback! We will consider this for our future release.
Regards,
Sangeet
Related Categories
-
Projects and billing
- 429 Conversations
- 176 Followers